TeraWulf Funds 760MW Gas Plant and Gives $100M in Utility Credits
From marketbrief.now
TeraWulf has agreed to fund a 760MW gas plant and provide $100M in utility credits to secure energy for its Muskie data center in Kentucky, which will double its contracted power capacity to 1 GW.
Read the sourceSign in to suggest
Sources
+ 3 more
- SUPPORT@matthew_sigel“large-load customers can “help reduce how fast rates might otherwise increase” and “help fund a stronger, more reliable grid,””x.com
- SUPPORT@matthew_sigel“WULF agrees to pay estimated financing costs associated with construction of Kentucky Power's ($AEP) planned 760MWs combined cycle generation facility at Big Sandy”x.com
- SUPPORT@stocksavvyshay“this 1 GW could support ~$2.4B of annual revenue once leased showing how valuable secured power has become in AI”x.com