title: "Oracle Invokes Force Majeure to Delay 2.45GW Data Center Payments"
lang: "en"
requested_lang: "en"
available_langs: ["en","vi"]
translation_fallback: null
fallback_fields: []
published_at: "2026-09-24T14:39:03.000Z"
category: "Infra"
topics: ["oracle","data-center","stargate","chips","infra","force-majeure","regulation","funding"]
source_urls: ["https://huggingnews.com/us-markets/oracle-invokes-force-majeure-to-delay-245gw-data-center-payments-448b3fca","https://x.com/wallstengine/status/2103100286638416088","https://x.com/firstadopter/status/2103101115138998541","https://x.com/TheStalwart/status/2103102615408308641","https://x.com/StockSavvyShay/status/2103100426245886095","https://marketbrief.now/us-markets/oracle-invokes-force-majeure-to-delay-245gw-data-center-payments-448b3fca","https://x.com/DeItaone/status/2103149999639113826","https://x.com/Amanda_Goodall/status/2103155095047442608"]
summary: "Shares of Oracle fell as much as 5.7% after the company notified the developer of its Project Jupiter site in New Mexico that it will seek to limit its costs if the facility fails to start operations by 2028. The company issued a force majeure notice to a unit of Blue Owl Capital to shield itself from expenditures and potentially delay financial obligations for the 2.45GW campus, which is part of the Stargate AI buildout. The development has faced regulatory setbacks, including the denial of a key energy permit and a six-month delay for a gas pipeline. Construction debt of $18B for the project is currently trading below 90 cents on the dollar, and Bloom Energy shares also declined since the project relies on its fuel cells. Oracle maintains that the facility remains on schedule and the company is fully committed to the New Mexico site."
---

# Oracle Invokes Force Majeure to Delay 2\.45GW Data Center Payments

> [Open the canonical story](<https://aidr.today/1b1ea9e4?lang=en>)

**Published:** 2026-09-24T14:39:03.000Z
**Category:** Infra
**Topics:** oracle, data\-center, stargate, chips, infra, force\-majeure, regulation, funding

## Summary

Shares of Oracle fell as much as 5\.7% after the company notified the developer of its Project Jupiter site in New Mexico that it will seek to limit its costs if the facility fails to start operations by 2028\. The company issued a force majeure notice to a unit of Blue Owl Capital to shield itself from expenditures and potentially delay financial obligations for the 2\.45GW campus, which is part of the Stargate AI buildout\. The development has faced regulatory setbacks, including the denial of a key energy permit and a six\-month delay for a gas pipeline\. Construction debt of $18B for the project is currently trading below 90 cents on the dollar, and Bloom Energy shares also declined since the project relies on its fuel cells\. Oracle maintains that the facility remains on schedule and the company is fully committed to the New Mexico site\.

## Sources

- [Story source](<https://huggingnews.com/us-markets/oracle-invokes-force-majeure-to-delay-245gw-data-center-payments-448b3fca>)
- [Supporting source](<https://x.com/wallstengine/status/2103100286638416088>)
- [Supporting source](<https://x.com/firstadopter/status/2103101115138998541>)
- [Supporting source](<https://x.com/TheStalwart/status/2103102615408308641>)
- [Supporting source](<https://x.com/StockSavvyShay/status/2103100426245886095>)
- [Story source](<https://marketbrief.now/us-markets/oracle-invokes-force-majeure-to-delay-245gw-data-center-payments-448b3fca>)
- [Supporting source](<https://x.com/DeItaone/status/2103149999639113826>)
- [Supporting source](<https://x.com/Amanda_Goodall/status/2103155095047442608>)